15men can complete a piece of work in25days. how many men should be added to complete the same work in15days.​

Respuesta :

mhanifa
mhanifa mhanifa
  • 04-08-2021

Answer:

  • 10 men

Step-by-step explanation:

Amount of work done by 15 men is:

  • 15 men *25 day = 15*25 man*days

Same work can be done by 25 men, in 15 days, so 10 more men should be added.

Answer Link
abovejosh
abovejosh abovejosh
  • 04-08-2021
Answer: 10 men explanation: guy above me
Answer Link

Otras preguntas

A given line has the equation 10x + 2y = −2. What is the equation, in slope-intercept form, of the line that is parallel to the given line and passes through th
I do not no what times to get to 16 and i can not ask my mom or dad or grandma or nobody becase they are working and i do not know nobody
Which of the following correctly describes seafloor spreading?
If the temperature of water is 82��c how far is the boiling point of water
1/12+3/8y=5/12+5/8y , what does y equal
Juanita is 13 years older than her cousin. The sum of their ages is no less than 103 years. What is the youngest age Juanita's cousin can be?
Two researchers are studying the decline of orangutan populations. In one study, a population of 784 orangutans is expected to decrease at a rate of 25 oranguta
Trace the patterns of early Indian history
Is a faded picture a chemical or physical change?
fifeteen more than half a number s 9