A critical activity is________________.a. an activity that consumes no time but shows precedence between events. b. a milestone accomplishment within the project. c. an activity with zero slack. d/ the beginning of an event.

Respuesta :

Ritmeks
Ritmeks Ritmeks
  • 09-03-2020

Answer:

C

Explanation:

Critical activity is the sequential activities from beginning to the end of a project. A lot of projects have a single critical path, although some projects may have more than one critical activity which depends on the flow logic utilized in the project.

Answer Link

Otras preguntas

pleaseee help asaaap its one little easy question plzzzz I would appreciate it and I give brainliest ^^!!
Determine whether the sample may be biased. Explain. Theo surveys every fourth person entering a grocery store to find out the average number of pets in people'
Barky's animal shelter has a total of 15 Chihuahuas and Yorkies. There are four times as many Chihuahuas as Yorkies. Using c for Chihuahuas and y for Yorkies,
I need help on homework.
what do you mean by bank​
what's 875,098 to the nearest 100 rounded?
Use a Punnett square to determine the genotypic and phenotypic ratios below. Phenotypic Ratios Genotypic Ratios Cross Trait Key Punnett Square % RR % Red % % Wh
literary techniques in to kill a mockingbird chapters 1 to ten?
The last one under m<1+m<3 is m<5+M<6
PLS HELP write a value that satisfies the equality Ix-3l=6